PROPOSED TIMETABLE FOR IMPLEMENTATION

TASK

START DATE

END DATE

STATUS

Consultation period

18/02/08

12/05/08

Complete

First Reading of legislation in Assembly

23/06/08

-------

Complete

Second Stage of legislation in Assembly (provisional)

01/07/08

-------

Complete

Committee Stage (provisional)

Sept 08

Nov 08

Complete

Consideration and Further Consideration Stages

Dec 08

Dec 08

Complete

Final Stage and Royal Assent

Jan 09

Feb 09

Complete

Subordinate legislation

Feb 09

March 09

Complete

Implementation

1 April 09

-------